Social Housing Construction Status Report Q1 2023

The latest Construction Status Report shows that 8,005 social homes were onsite at the end of Quarter 1 2023 with an additional 13,269 homes at design and tender stage. In Quarter 1 2023, 121 new construction schemes, (1,564 homes) were added to the pipeline.

Data Resources (2)

CSV
Q1 2023 CSR
XLXS
Q1 2023 CSR

Data Resource Preview - Q1 2023 CSR

Data Owner Social Housing Delivery Co-Ordination Unit
Data Owner Email housingdeliveryco-ordination@housing.gov.ie
Theme Housing
Date released 2023-09-22
Date updated 2023-09-22
Update frequency Quarterly
Language English
Provenance information DHLGH
Period of time covered (begin) 2023-01-01
Period of time covered (end) 2023-03-31